Are your plans ready to bid? Twelve checks before you ask for a price

A builder can only price what is drawn. If the set is missing sheets or disagrees with itself, every bid will be built on guesses, and the guesses come back later as change orders. Run these twelve checks first. Most take minutes.

Building

The short answer: a set is ready to bid when every listed sheet is there (dimension plan, structural, electrical, energy, survey and drainage), the schedules match the plans, the notes agree with each other and the clearances meet code. If it fails some checks, send questions back to the architect before anyone prices it.

Send your plans to Matt

The sheets that should be there

  1. A title sheet with the code data, the fire sprinkler answer and the list of every sheet. Check that every listed sheet is actually in the set.
  2. A dimension plan, not only a floor plan. Walls and openings should be dimensioned to grid lines, not left to scale.
  3. The structural sheets: foundation plan, framing plan, shear walls, hold-downs and details, stamped by the engineer.
  4. Electrical, lighting and mechanical plans, or a written note that the builder is to design them.
  5. The energy report (Title 24), which sets insulation, windows and equipment. What the 2025 code asks.
  6. A survey and a grading and drainage plan, with the stormwater plan where required.

The conflicts to look for

  1. Schedules against plans. Every door and window size in the schedule should match the opening drawn on the plan.
  2. Structure against architecture. A shear wall or a beam should not run through a window, a stair or a duct.
  3. Notes against notes. The same item, such as a vapor retarder, a fire-rated assembly or a column count, should say the same thing on every sheet.
  4. Clearances. Toilets, showers, stairs and landings drawn to the code minimums, not just close to them.

The decisions to make before pricing

  1. Finishes with a real description or an allowance that says what it buys: tile, plumbing fixtures, lighting, appliances, cladding.
  2. The long-lead items: windows, doors, steel and specialty equipment, chosen or at least specified by performance.

If the set fails some checks

That is normal. Almost every set does, and it is far cheaper to know now. Send the open items back to the architect as questions, each with the sheet and who answers it, and price only once the answers are in or carried as named allowances.

We do this with a 3D model built from the full set and checked against every sheet. On a 35-sheet ADU it raised 49 questions. How we build it first.

General guidance for owners on the Santa Barbara South Coast. Which sheets a jurisdiction requires depends on the project. Check the submittal checklist of your City or County.

Related: preconstruction for a custom home, how to avoid change orders and how we work with architects.

Ask Matt about your project More writing

Built by Matt Newman. Licensed since 2002. Salt Lake City, Los Angeles, twenty years on this coast, and on every AMN site himself. One name on the contract. His story

Inquiries

Send us your plans. We will run the checks for you.

Email the set, or a link to it, to purchasing@amnbuild.com. Matt reads it himself and writes back within two business days.

  1. Same dayMatt confirms he has it, and flags anything obvious that is missing.
  2. Within two business daysA written answer: what we see in your plans or your parcel, an order of cost, and the next step.
  3. Then nothing, unless you askNo follow-up sequence, no call from anyone else. The reading is yours to keep.

CSLB 802739 · Class B General Building · Licensed and insured · Two-year workmanship warranty, in writing

Updated November 2026