Change orders on a custom home: where they come from, and how to stop most of them

A change order is not a sign of a bad builder or a bad owner. It is a price that was not settled before the work. Most of them can be seen coming, if you look in the right three places before you sign.

Building

The short answer: most change orders come from gaps in the drawings, low allowances and late decisions. Get a written list of what is unclear before the price, allowances that say what they buy and when to decide, and decisions scheduled in build order.

Send your plans to Matt

They come from three places

The drawings. Two sheets disagree, a dimension is missing, a detail is "see structural" and the structural sheet does not show it. The builder prices one reading, and the field finds another. Industry studies, mostly of commercial building, put direct rework at around 5 percent of construction cost, and much of it traces back to design and documentation.

Allowances. An allowance is a placeholder sum for something not chosen yet, like tile, fixtures or lighting. If it is set low to make the number look good, every selection becomes an increase.

Late decisions. A choice made after the wall is closed is a change, even when the price of the item is the same, because work is torn out and done twice.

Close the drawings before the price

Ask your builder to read the whole set, not just the floor plan, and to hand you a written list of what is unclear before they price it. Each item should name the sheet, who answers it, and whether it changes the price.

We go further: we build the house as a 3D model from the full set and check it against every sheet. On a 710-square-foot ADU with 35 sheets, that found 49 questions, including a shear wall drawn through a window and a door scheduled wider than its opening. How we build it first.

Make the allowances honest

  • Every allowance should state what it buys: a quantity and a level, not just a dollar figure.
  • Every allowance needs a date to decide by, tied to the build step that needs it.
  • Ask what happens to money you do not spend. In our contracts, credits go back to you in full. Our allowance schedule and change-order clause.

Decide in the order the house is built

Windows and doors come before framing is finished. Plumbing fixtures come before rough-in. Tile comes before the walls are waterproofed. A schedule of owner decisions, each with "decide before step N", turns this from a surprise into a calendar.

Fixed price, cost-plus, or a cap

A fixed price puts the risk of the builder's own mistakes on the builder, but only for what the drawings show. It is only as good as the set it was priced from. Cost-plus passes every cost to you, with a fee on top. It suits work that cannot be defined yet, and it needs open books. A guaranteed maximum price caps cost-plus, and the cap is only real if the scope is.

Whichever you sign, the protection comes from the same place. First, drawings that have been checked. Second, a clause that says no work that changes the price goes ahead until you approve it in writing. The three contracts compared.

What to ask before you sign

  • What did you find unclear in my drawings, in writing?
  • Which of your numbers are allowances, and what does each one buy?
  • When must I make each decision?
  • What happens to unspent allowance money?
  • Can work that changes the price start before I approve it in writing?
Sources: Hwang and others, Journal of Construction Engineering and Management 135(3), 2009 (rework of about 5 percent of construction cost across 359 projects); NAHB, "Minimizing change orders by being upfront" (opens in a new tab). General information for homeowners, not legal advice.

Related: build it first, our change-order clause and preconstruction for a custom home.

Ask Matt about your project More writing

Built by Matt Newman. Licensed since 2002. Salt Lake City, Los Angeles, twenty years on this coast, and on every AMN site himself. One name on the contract. His story

Inquiries

Send us your plans. We will tell you what is in them.

Email the set to purchasing@amnbuild.com. Matt reads it himself and writes back within two business days.

  1. Same dayMatt confirms he has it, and flags anything obvious that is missing.
  2. Within two business daysA written answer: what we see in your plans or your parcel, an order of cost, and the next step.
  3. Then nothing, unless you askNo follow-up sequence, no call from anyone else. The reading is yours to keep.

CSLB 802739 · Class B General Building · Licensed and insured · Two-year workmanship warranty, in writing

Updated November 2026