Fixed price, cost-plus or a guaranteed maximum? Who carries the risk, and when each fits

The three contracts move risk between you and the builder in different ways. None of them is safe on its own. Each depends on how complete the drawings are and on what the contract says about change.

Contracts

The short answer: a fixed price puts the builder's own risk on the builder but only covers what is drawn; cost-plus puts every cost on you; a guaranteed maximum caps cost-plus. All three are only as safe as the drawings are complete and the change clause is clear.

Send your plans to Matt

The three, side by side

Three ways to price a house
ContractHow the price worksWho carries the riskFits when
Fixed priceOne sum for the work drawnThe builder, for its own costs and mistakes, within the drawn scopeThe drawings are complete and checked
Cost-plusActual cost plus a feeYou, for every costThe scope cannot be defined yet, and the books are open
Guaranteed maximum (GMP)Cost-plus with a capShared: the builder above the cap, you below itThe scope is defined enough to cap, with a stated contingency

Fixed price

A fixed price protects you from the builder's own estimating errors and price rises, for what the drawings show. It does not protect you from what the drawings leave out: those come back as change orders. A fixed price on an incomplete set is a bid that will be corrected later, at your expense.

Cost-plus

You pay what the work costs, plus a fee or a percentage. You see every invoice, and you pay for every surprise. It suits work that cannot be defined until walls are open. It needs open books, a budget you track monthly and a fee that does not grow because costs do.

Guaranteed maximum price

A GMP caps cost-plus. Savings below the cap usually return to you, sometimes shared. The cap is only as real as the scope behind it, and a large "contingency" inside the cap is where the risk hides. Ask what the contingency is for and who decides how it is spent.

How we price

We give ranges until the trades have bid the permitted set. At Phase 05 the price becomes one fixed sum, and after that it moves only by a change you approve in writing before the work. Before we fix it, we build the house as a 3D model from the full set and check it against every sheet. That way the fixed price covers the house that will actually be built. Our change-order clause · Build it first.

General information for owners, not legal advice. For your own contract, ask a construction attorney.

Related: how to avoid change orders, are your plans ready to bid? and owner's rep, construction manager, general contractor.

Ask Matt about your project More writing

Built by Matt Newman. Licensed since 2002. Salt Lake City, Los Angeles, twenty years on this coast, and on every AMN site himself. One name on the contract. His story

Inquiries

Send us your plans. We will tell you what they can be priced as.

Email the set to purchasing@amnbuild.com. Matt reads it himself and writes back within two business days.

  1. Same dayMatt confirms he has it, and flags anything obvious that is missing.
  2. Within two business daysA written answer: what we see in your plans or your parcel, an order of cost, and the next step.
  3. Then nothing, unless you askNo follow-up sequence, no call from anyone else. The reading is yours to keep.

CSLB 802739 · Class B General Building · Licensed and insured · Two-year workmanship warranty, in writing

Updated November 2026