The loop
Refrigerant is pumped around a closed loop between an outdoor coil and an indoor coil. Where it evaporates, it absorbs heat; where it condenses, it releases heat.
WhyMoving heat takes far less electricity than making it. A heat pump can deliver several units of heat for each unit of electricity.
Reverse it for cooling
A reversing valve swaps the roles of the two coils, so the same machine heats in winter and cools in summer.
Indoors: the air handler
A fan pulls house air through a filter and across the indoor coil, then pushes it through supply ducts to the rooms; return ducts bring it back.
Floor furnaces and wall heaters
Many South Coast houses from the 1920s to the 1960s were heated by a gas floor furnace in the hallway or wall heaters in a few rooms, with no ducts and no air conditioning.
WhyOld floor furnaces and wall heaters are worth a safety check: cracked heat exchangers and poor venting can leak carbon monoxide.
Forced air
A furnace or heat pump with ducts to every room. Common from the 1960s on, often in the attic or crawlspace.
Ductless and radiant
Mini-splits mount a small head in each room and need no ducts, which suits older houses. Radiant floors circulate warm water in tubing under the floor.
Fresh air
An energy or heat recovery ventilator brings in outdoor air and exhausts stale air, swapping heat between the streams.
WhyTighter houses need deliberate ventilation; California requires whole-house mechanical ventilation in new homes.
Six stations
Galvanized coil is sheared, rolled into round or rectangular duct, seamed, formed into elbows and boots, and wrapped in insulation for runs through attics.
Flex duct
Flexible duct is a wire helix in plastic film, wrapped in insulation and a vapor jacket. It is quick to install and loses airflow when kinked or sagging.
Size from a load calculation
Equipment is sized from a room-by-room heat load calculation, not from the old unit’s label. Oversized units short-cycle, dehumidify poorly and wear out sooner.
Seal and test the ducts
Every joint is sealed with mastic or listed tape, and new or altered systems are leak-tested by a HERS rater under California’s energy code.
Commission it
Gauges on the line set confirm the refrigerant charge, airflow is measured at the coil, and the owner is shown the filter and the controls.
Chapter 5 of 7
A hundred years of South Coast comfort.
For most of the century, many houses here had no cooling at all, and a single heater.
1920s: fireplaces
Spanish Colonial Revival houses relied on fireplaces and, sometimes, a basement gravity furnace.
1940s: the floor furnace
A gas floor furnace under a hallway grille heated many modest houses: one hot spot, no ducts.
1960s: forced air
Furnaces with attic ducts spread through tract houses; ducts were rarely sealed.
1990s: air conditioning
Central air conditioning became more common as inland heat waves reached the coast.
2026: heat pumps by default
The 2025 Energy Code, effective 1 January 2026, sets heat pumps for space and water heating as the baseline for new homes. Gas designs must make up the difference elsewhere.
Chapter 6 of 7
The same trade, on a real ADU.
Every course ends on one building: a 710-square-foot ADU on Canon Drive in the Santa Barbara foothills, modelled from its permit set before pricing. Three gables, three floor levels, a steel canopy, and a list of questions the drawings left open. Here is heating, cooling and fresh air in 710 square feet.
Three heads, one outdoor unit
The proposed layout has a ductless head in the living room, the bedroom and the primary, all on one three-zone outdoor unit on a pad north of the bath. Final sizing comes from the mechanical engineer's load calculation.
Line sets outside the wall
The line sets leave each head through the north wall and run in a painted cover down to the outdoor unit, never across a window or a door.
160 cfm, not 100
For a home under 750 square feet with an electric range, the 2022 Energy Code calls for a range hood rated 160 cfm or 65 percent capture efficiency. This ADU is 710 square feet; an earlier version of our model said 100 cfm, and we corrected it.
Two bath fans
Each bathroom gets an ENERGY STAR fan with humidity control, ducted to an ember-resistant roof jack. The fans and the hood were required but not drawn, so we located them.
Replace a furnace with a heat pump
In a house with ducts, a ducted heat pump can replace the furnace and add cooling. The ducts are tested, sealed, and often replaced if they are old flex duct.
No ducts? Go ductless
Older houses without ducts are good candidates for mini-splits: small heads in key rooms, one outdoor unit, no walls torn open.
A ductless install
A mini-split puts a head high on an inside wall (seen here from inside the room) and an outdoor unit on a pad or bracket just outside. Between them runs a line set: two refrigerant lines, a power cable and a condensate drain, through one small hole and up the outside wall in a painted cover. The drain runs to daylight or a small pump.
WhyOn a historic front wall a line-set cover is a design review item. Route it on a side or rear wall, or inside a closet.
Ventilation you can see
A tight house needs planned air: a balanced ventilator (an ERV or HRV) brings fresh air in and sends stale air out, trading heat between the two streams; the range hood and every bath fan are ducted all the way outside, not into the attic. California requires whole-house ventilation in new homes and a hood that vents outdoors.
WhyA gas range without a ducted hood is the biggest indoor air problem in many kitchens. In a remodel, the hood duct route is planned with the cabinets.
Radiant floors, up close
Radiant heat runs warm water through loops of PEX tubing laid over insulation and buried in a thin pour or set in grooved panels. Each loop starts and ends at a manifold, and a heat pump or boiler heats the water to well under bath temperature. Tile or engineered wood goes on top; thick carpet works against it.
WhyRadiant is slow to warm and slow to cool, so it is set and left alone. It pairs well with a heat pump water heater and with the tile floors common in Spanish Colonial Revival houses.
Electrical capacity
Heat pumps, heat-pump water heaters and induction cooking can push an older 100-amp service past its limit; a load calculation decides. The Cannon Drive ADU takes its power as a feeder from the main house; the feeder route and panel size are still open questions on its plans.
Air has to get back
Every room that gets supply air needs a way for it to return. In a house with one central return in the hall, a bedroom with its door shut fills up with air and the supply slows; a jumper duct or transfer grille over the door lets it flow back. Good duct design sizes returns as carefully as supplies.
WhyA bedroom that is always stuffy with the door closed, or a door that whistles, is usually a missing return path.
Filters and smoke days
Wildfire smoke reaches every South Coast house some years. A MERV 13 filter catches most fine smoke particles, but it resists airflow, so the filter slot is sized for it, ideally a deep media filter, and the fan set to run. Portable HEPA cleaners in bedrooms fill the gap in houses without ducts.
WhyA thick filter jammed into a slot made for a thin one starves the system of air. Size the filter rack when the duct system is designed.
Thermostats and zones
One thermostat in the hall cannot keep a sunny addition, a shaded bedroom wing and an upstairs all comfortable. Zoning splits the house: each zone has its own thermostat, and dampers in the ducts or separate ductless heads deliver heat or cooling only where it is called for.
WhyMost comfort complaints in remodeled houses come from new rooms added to an old system with one thermostat. Zones are planned with the duct design.
Big range hoods need make-up air
A professional range hood can pull many hundreds of cubic feet of air a minute out of a tight house. The residential code requires make-up air for any kitchen hood able to exhaust more than 400 cfm: a duct with a motorized damper, often with its own heater or tempering, interlocked so it opens when the hood runs. Without it the hood starves, doors whistle, and a fireplace or gas appliance can be drawn backward into the room.
WhyThe hood is chosen by the designer and the make-up air by the mechanical engineer. One of them has to tell the other.
Wine rooms
Wine keeps best cool and steady, around 55 degrees and fairly humid. A wine room is built like a small refrigerator: a vapor barrier on the warm side of every wall and the ceiling, thick insulation, an exterior-grade door with weatherstripping, and a cooling unit made for cellars, which works at those temperatures without drying the air. Ordinary air conditioning is the wrong tool; it runs too warm and too dry.
WhyThe vapor barrier is the step that gets missed. Without it, the cold room pulls moisture into its own walls.
Humidity for art, wood and instruments
Paintings on wood panel, antique furniture, wood floors and pianos all swell and shrink with humidity. On the coast the air is damp most of the year and very dry on Santa Ana or sundowner days. Rooms that hold collections get humidity sensors and a system that can add or remove moisture, sized by the mechanical engineer, not only a thermostat.
WhyA stable 40 to 55 percent relative humidity protects floors and casework as much as art. Ask the collector what range their conservator wants.
Pull a vacuum
A heat pump or air conditioner is a sealed loop, and it is only as good as the day it was sealed. The installer brazes the copper line set while flowing nitrogen through it so no scale forms inside, pressure-tests the joints, then pulls a deep vacuum with a pump and a micron gauge to boil off moisture and air. A common target is 500 microns, and the gauge has to hold near that after the pump is valved off; if it climbs, there is a leak or moisture. Only then is the refrigerant released.
WhyMoisture left in a system turns to acid and kills compressors years later. Ask to see the micron reading, not just "it's cold".
J, S and D
Good heating and cooling is designed in three steps that come from the industry's ACCA manuals. Manual J calculates the heating and cooling load room by room from the walls, windows, orientation and climate. Manual S picks equipment sized to that load, not to the old unit or a rule of thumb. Manual D sizes the ducts and registers so each room gets its share of air at a pressure the equipment can deliver. Oversized equipment short-cycles, dehumidifies poorly and is noisy.
WhyOn the mild South Coast oversizing is the common mistake. Ask for the Manual J before anyone quotes a tonnage.
Condensate goes somewhere
An air conditioner or heat pump pulls water out of the air, gallons a day in humid weather, and that condensate has to drain. The primary drain is trapped, sloped and run to an approved place. Where the unit sits over a finished ceiling, as in an attic, the mechanical code asks for a backup: a secondary pan with its own drain to a visible spot, or a float switch that shuts the unit off when water rises. A clogged drain with no backup is a stained ceiling.
WhyIf water drips from the secondary drain outlet, the primary is blocked. Tell the owner what that drip means.
Fans go outside
A bath or laundry fan moves wet air, and the code requires it to discharge outdoors, through a duct to a roof or wall cap with a backdraft damper. Fans that blow into the attic, or ducts that end near a soffit vent and blow back in, soak the insulation and grow mold on the roof sheathing. The duct should be as short and straight as practical, insulated where it crosses a cold attic, and sized as the fan maker asks.
WhyCheck every fan duct in the attic before insulation. A disconnected one is easy to fix now and expensive later.