Most remodel budgets that go wrong go wrong behind the plaster. In a house built before the 1980s the same few things turn up again and again. None of them has to be a surprise: almost all can be found, or at least bounded, before a price is fixed.

Renovation

The short answer: in a house built before the 1980s expect some of old wiring, galvanized or cast-iron pipe, a cracked sewer line, lead paint, asbestos, rot and termite damage, earlier unpermitted work and an unbolted foundation. Open a few walls, the panel, attic and crawl space and camera the sewer before a price is fixed.

Send your plans to Matt

Wiring

Knob-and-tube wiring, ungrounded circuits and old panels are common in houses from before the 1960s. A kitchen or bath remodel usually means new circuits back to the panel, and often a new panel and service. Open a few outlets and the panel cover early, and the scope is known.

Pipes and the sewer line

Galvanized steel supply pipe narrows with rust from the inside; cast-iron and clay drain lines crack and take in roots. A camera run down the sewer line to the street costs little and settles one of the most expensive unknowns before the price, not after the trench is open. Inside the City of Santa Barbara it can also be required: a permit for 400 square feet or more of construction, or two or more plumbing fixtures, opens a case under the City's Sewer Lateral Inspection Program, and the owner repairs what the video finds, because the owner owns the line up to and including the connection at the main.

Lead paint and asbestos

A house built before 1978 is treated as having lead paint: the federal rule requires work that disturbs it to be done by a certified firm with lead-safe practices. Asbestos can be in old flooring, textured ceilings, duct wrap and plaster. We test before anything is disturbed. A single house is often exempt from the federal asbestos notice, but the County air district asks owners to check with it before renovating or demolishing.

Rot, termites and earlier work

Water finds the same places: under windows and doors, at the base of stucco walls, under showers and around old decks. Termite damage follows. So does earlier work done without a permit, which may have to be brought up to code once the wall is open. A pest report and a look at the permit history show most of it.

Foundations and the frame

Older houses may sit on unreinforced or unbolted foundations, with short cripple walls and few or no shear walls. A remodel that opens the walls is the cheapest time to bolt and brace, and a large enough remodel can require it. Undersized framing turns up where earlier owners moved walls or added weight.

How we price it

We open walls on purpose during feasibility: a few small holes in the right places, the panel, the attic, the crawl space, and a camera down the sewer. What we cannot see is named in the contract with an allowance and a stated contingency, so you know before the start what is fixed and what is still a range. Renovations, and remodel or rebuild when the list gets long.

Related: remodel or rebuild in Montecito, avoiding change orders and kitchen remodels

Ask Matt about your project More writing

Built by Matt Newman. Licensed since 2002. Salt Lake City, Los Angeles, twenty years on this coast, and on every AMN site himself. One name on the contract. His story

Inquiries

Send us the address. We will look behind the walls first.

Email purchasing@amnbuild.com with the address and what you are thinking of changing. Matt reads it himself and writes back within two business days.

  1. Same dayMatt confirms he has it, and flags anything obvious that is missing.
  2. Within two business daysA written answer: what we see in your plans or your parcel, an order of cost, and the next step.
  3. Then nothing, unless you askNo follow-up sequence, no call from anyone else. The reading is yours to keep.