AMN Construction
AMN Construction · Writing · Timeline

How long a custom home takes on the South Coast: seven phases, and where the time goes

From the first conversation to moving in, a custom residence here typically takes 17 to 34 months. Construction is usually not the longest part. Review is. Here is the road phase by phase, with the time each phase usually takes and where time is lost.

Timeline

The short answer: a custom residence on the South Coast typically takes 17 to 34 months from the first conversation to move-in. Design review and permits are usually the longest stretch, and the November-to-April rainy season shapes when digging can start.

Send your plans to Matt

The seven phases

Typical durations, custom residence, South Coast
PhaseTypical timeWhat happens
01 The parcelTwo business daysA written reading of what the ground allows
02 FeasibilityOne to four weeksBudget, review path and schedule for this site
03 Design developmentFour weeks to four monthsThe architect develops the design, with the builder at the table
04 EntitlementSix weeks to nine monthsDesign review, plan check and permits
05 PreconstructionTwo to four weeksTrades bid the permitted set and the price is fixed
06 ConstructionThree to eighteen monthsThe house is built
07 ClosingOngoingFinal inspection, punch list, warranty

The ranges cover our three kinds of work. A custom residence sits toward the long end of each, and the full road is typically 17 to 34 months. The seven phases in full.

Why review takes the longest

A Montecito house goes to the County and to the Montecito Board of Architectural Review. In the City of Santa Barbara, most exterior work goes to the Single Family Design Board, or to the Historic Landmarks Commission in El Pueblo Viejo. Near the coast, a coastal development permit can add a hearing and an appeal period. Hearing calendars set the pace, not plan check. Who reviews what, town by town.

The rainy season

The County's grading code requires erosion controls from November 1 to April 15. A start that puts the excavation in that window costs more and can slip with every storm. Planning the permit date backward from a spring or summer dig often saves more time than any shortcut in construction.

Where time is usually lost

  • Drawings that go back and forth. Every round of plan-check comments is weeks. A set checked before submittal comes back with fewer.
  • Late decisions. Windows, doors and steel have long lead times. Chosen late, they hold the frame open.
  • Problems found on site. A conflict between two sheets found by a framer stops a crew and starts a redesign.

All three are cheaper to settle before ground breaks. We build the house as a 3D model from the full set and check it against every sheet during design and preconstruction. How we build it first.

Put your own dates on a calendar

Our calendar tool lays the phases on real months from the month you first call, with the rainy season marked.

Durations are AMN Construction's published typical ranges, from our own projects, and are the same ones on our process page. They are not a schedule for any house. Rainy season: County of Santa Barbara grading code.

Related: how to read a construction schedule, what a custom home costs here and preconstruction for a custom home.

Ask Matt about your project More writing

Built by Matt Newman. Licensed since 2002. Salt Lake City, Los Angeles, twenty years on this coast, and on every AMN site himself. One name on the contract. His story

Inquiries

Send us the address. We will lay out your road.

Email it to purchasing@amnbuild.com. Matt reads it himself and writes back within two business days.

  1. Same dayMatt confirms he has it, and flags anything obvious that is missing.
  2. Within two business daysA written answer: what we see in your plans or your parcel, an order of cost, and the next step.
  3. Then nothing, unless you askNo follow-up sequence, no call from anyone else. The reading is yours to keep.

CSLB 802739 · Class B General Building · Licensed and insured · Two-year workmanship warranty, in writing

Updated November 2026