Seven phases
AMN runs every project in seven phases: the parcel, feasibility, design development, entitlement, preconstruction, construction, and closing and warranty.
Every other course in this school is one trade. This one is the sequence: who goes when, what has to be approved before what, and how the money and the schedule are kept honest. It walks AMN’s seven phases, the inspections that gate construction, and a century of rules that made building on the South Coast what it is.
The 3D scenes need WebGL, which this browser has turned off. Every word of the course is still here on the left.
Like a wall assembly, a project has layers, and each one rests on the one below.
AMN runs every project in seven phases: the parcel, feasibility, design development, entitlement, preconstruction, construction, and closing and warranty.
There are three planned exits: after feasibility, after design development, and after entitlement. At each one the owner keeps every report, drawing and permit produced.
WhyThe cheapest time to stop a project that does not work is before anything is built.
In preconstruction the trades bid the permitted drawings, and the contract sum becomes binding.
Six communities, several authorities. Knowing which one applies is the first job of the parcel phase.
In the city, single-family design goes to the Single Family Design Board; in El Pueblo Viejo and for landmarks, the Historic Landmarks Commission.
Santa Barbara: The city formed its Architectural Board of Review in 1925, within weeks of the earthquake, often described as the first in the country.
Montecito is unincorporated county land, reviewed by the County Board of Architectural Review. Hope Ranch reviews through its Park Homes Association, then the County.
All of Carpinteria lies in the Coastal Zone, and parcels near the shore elsewhere may need a Coastal Development Permit under the 1976 Coastal Act.
Construction runs in order, like a line, except the house stands still and the trades move through it. Each model is the same house one stage further along, read left to right, back row first.
Layout, foundation, framing, roof and windows, rough-in of the systems, rough inspections, insulation and drywall, finishes, and the final inspection and punch walk.
Inspections gate the work: foundation before the pour, frame and rough-in before insulation, insulation before drywall, and the final. Covering work before its inspection means opening it back up.
Windows, cabinets, stone and some equipment take weeks or months. They are ordered in preconstruction so they arrive when their station comes.
Owners want to know three things every week: what happened, what is next, and what it cost.
Matt writes to every owner every Friday: progress, the next two weeks, decisions needed and costs.
Changes are priced and signed before the work is done. California’s home improvement contract rules spell out what a contract and change order must contain.
Progress payments follow completed work, with conditional and unconditional lien releases from subcontractors and suppliers.
Most of what makes building on the South Coast slow, and good, was added after something went wrong.
After the June earthquake, the city created its Architectural Board of Review and rebuilt State Street in the Spanish Colonial Revival style.
The city adopted El Pueblo Viejo district guidelines to protect the Spanish Colonial Revival character of downtown.
The California Coastal Act created permanent coastal-zone review, which still shapes building near the shore from Goleta to Carpinteria.
California’s first building energy standards made insulation and efficient windows part of every permit.
Wildland-urban interface standards (2008) and sprinklers in new homes (2011) changed foothill construction.
The 2025 California building codes took effect on 1 January 2026, with heat-pump baselines, battery readiness and updated wildfire rules.
Every course ends on one building: a 710-square-foot ADU on Canon Drive in the Santa Barbara foothills, modelled from its permit set before pricing. Three gables, three floor levels, a steel canopy, and a list of questions the drawings left open. Here is the job as 14 steps and a list of questions.
Site prep, underground, footings, slabs, wall framing, roof framing, dry-in, rough-in, insulation, drywall, exterior finishes, interior finishes, trim and equipment, and site concrete with the final. Each step has its trades, its deliveries and its inspection.
We sent back the open items before pricing: missing sheets, conflicting floor levels, the sprinkler question, the escape window, the landing, the toilet clearance and the cladding in the fire zone. Each item names who answers it and which trades it touches. Submittal 3 answered ten of them, the sprinklers and the escape window among them.
WhyQuestions asked before the bid cost nothing. The same questions asked after the frame cost change orders.
Some answers belong to the owner: the finishes, the plaster color, where every towel bar and the TV go. Each one has a latest date in the schedule, usually before insulation.
Site concrete, the handrail, the finish grade falling away from the walls, a punch list and the owner walkthrough. Then the building final.
The best predictor of a smooth project is how much is known before construction starts.
Zoning, setbacks, slope, soils, the Coastal Zone, fire hazard maps and design review all come from the parcel. We read them before design begins.
Windows, cabinets, stone, fixtures and equipment are chosen in design development and ordered in preconstruction, so construction is not waiting on decisions.
A construction schedule is a set of bars: each task, when it starts and how long it takes. The chain of tasks that each wait on the one before, foundation, framing, rough-in, drywall, finishes, is the critical path; a day lost there is a day lost at the end. Long-lead orders like windows and cabinets run alongside and must land before their bar starts.
WhyMost delays are a decision that came late, not a slow crew. The schedule shows which decisions are due when.
A change starts as an owner request or something found in the walls. It is priced in money and days, the owner signs it, and only then is the work done. It then shows on the next invoice as its own line, so the contract total always matches what was signed.
WhyCalifornia home improvement law requires changes to be in writing and signed. A change done on a handshake is the most common source of end-of-job disputes.
Matt Newman, the principal, walks the parcel, prices the work, signs the contract and runs every AMN site.
A job ends with a binder, paper or digital: the signed final inspection, manuals and warranties for every appliance and system, photos of every wall before drywall, paint colors and tile and stone lot numbers, where every shutoff is, and lien releases from every subcontractor and supplier. Then a walk-through at a few months and again near a year.
WhyPhotos of the open walls are the most useful thing in the binder. They show where every pipe, wire and blocking runs, years later.
Before work starts the site is fenced and screened. Storm-water rules (a SWPPP on larger sites) call for fiber rolls along the low edge, a rock entrance so trucks do not track mud into the street, protected storm drain inlets, and covered bins with concrete washout kept away from drains. Open edges on upper floors get guardrails or other fall protection under Cal/OSHA rules.
WhyMud in the street and a fall from a second floor are the two things that stop a job fastest. Both are cheap to prevent.
Near the end, the superintendent and the owner walk every room and mark each small fix with blue tape: a paint touch-up, a sticking drawer, a missing cover plate. Each item is closed and signed off. Then the house is cleaned top down with HEPA vacuums and damp wipes, and the floor protection comes up last.
WhyDust from sanding and cutting settles for days. Cleaning before the last trades leave means cleaning twice.
An estimate is a row of parts (drawn here roughly to the share each often takes; every house differs): site work and foundation, framing and roof, windows and doors, the systems, insulation and drywall, finishes, the allowances an owner still has to choose, then overhead, contingency and fee. Each line comes from takeoffs and subcontractor quotes on the drawings, not from a price per square foot.
WhyAllowances are where budgets drift. Choosing tile, fixtures and appliances before the contract turns a guess into a number.
Before a material is ordered, the contractor submits its data sheets and samples for the architect and owner to approve. Finishes that are hard to describe, like plaster texture, stain color or the grout joint in a stone wall, get a mockup: a real piece built on site with the real crew. The approved sample is signed and dated and kept on site; everything that follows is judged against it.
WhyA mockup turns "I don't like it" from the end of the job into the beginning, when it costs a panel, not a house.
Late in a job, finished floors, cabinets, stone and doors are in place while trades are still working around them. Floors get a breathable protection board taped at the seams, never plastic sheeting over a fresh finish; cabinet and stone faces are wrapped; door edges get guards; and walk-off mats mark where boots stop. Protection is checked daily and replaced when damaged.
WhyRepairing a gouged floor or a chipped slab costs more than protecting a whole house. It is in the schedule and the budget.
Every trade works to a tolerance: how far out of level, plumb, flat or square its work may be. Framing, concrete, drywall, tile and cabinetry each have their own, and the finer finishes need the work under them to be tighter than its own standard. On a high-end job the tolerances are written down, one level benchmark is set for the whole house, and each trade checks the work it receives before covering it.
WhyMost finish problems are inherited. The cabinetmaker cannot fix a wall that is out of plumb; the framer could have, for free.
California gives the trades strong payment tools, and each depends on the one before. A subcontractor or supplier serves a preliminary notice on the owner, the general contractor and any lender within 20 days of first furnishing work or material; a late notice only protects the 20 days before it. A sub records a mechanics lien after finishing its work, within 90 days of completion of the project, or within 30 days if the owner records a notice of completion, then must sue to enforce it within 90 days of recording. Waivers are signed on the statutory forms, and only conditional ones until the money has cleared.
WhyFinish trades arrive last, when the budget is spent, and a recorded notice of completion can shorten their window to 30 days. Calendar it the day the work ends. This is general information, not legal advice.
Santa Barbara: Most South Coast custom homes are private jobs with a construction lender and no payment bond, so the notice and the lien are the trades' main security.
People plan a job from the inside: the steps, the crew, the materials. They leave out the rot behind the plaster and the tile that gets changed. In a well-known study, students expected to finish a thesis in about 34 days and took about 55; fewer than half beat even their own worst case. The fix is to start from how similar finished jobs actually went: collect actual-to-estimate ratios for jobs like this one, read off the middle (P50) and the 80th percentile (P80), then adjust a little for what is truly different.
WhyPlan the crew to the P50, quote the owner the P80, write both down before work starts, and score the job when it ends. The record makes the next estimate honest.
Quality on a fine house is not inspected in at the end. Two rules produce most of it. First, benchmark first: no trade starts production until its first unit, the first plaster wall, stone return, cabinet run or tile field, is built, reviewed and signed as the standard. Second, hold points: a published list of moments when work may not continue without an inspection, such as waterproofing before it is covered, framing before insulation, rough-in before the walls close, and slab preparation before the pour.
WhyThe most dangerous sentence on a site is "close it up, the inspection can float." The hold point exists for the day it is inconvenient. Hold it.
Water is the trade that works nights, weekends and the ten years after the job closes. On houses with wine rooms below grade, planters over living space, pools on hillsides and flat roofs behind parapets, the practice is the same every time: one person accountable for the whole envelope, redundant layers below grade, a flood test held for days on every deck, shower pan and planter before it is covered, electronic leak scans on flat roofs, and every window and door set the way the tested mockup was, with a sill pan.
WhyNone of this is exotic. It is rare only because it means saying no to schedule pressure at the moment the pressure is highest.
Estate lanes in Montecito and Hope Ranch were laid out for carriages, and a big house moves thousands of truckloads down them. The site logistics plan is a neighbor plan: set haul routes and delivery windows, crew parking off site with a shuttle instead of trucks lining the lane, flaggers on concrete and steel days, wheel washing and street sweeping when grading, crane lifts with written notice to the neighbors, and dust control that actually runs.
WhyEvery one of these is a line in the estimate. Every one buys the quiet in which a reputation grows.
A three-year house is managed by rhythm. The weekly owner, architect and builder meeting runs a fixed agenda: safety and site, the schedule and the weeks ahead, budget and changes, decisions due with dates, quality and mockups, neighbors, and actions. Minutes go out within a day. Once a month a report arrives on the same day in the same format: a short plain summary, the budget with approved and pending changes and the forecast at completion, cash against plan, the schedule against the baseline, decisions needed with the cost of waiting, the top risks, and photographs.
WhyPredictability is the message. Whoever writes the minutes holds the project's memory.
Changes do not destroy an owner's trust; surprises do. When something goes wrong, call before you write, so the owner never reads important news cold. Bring the problem, its rough size in cost and time, and a recommendation together. Follow the call with a written summary, and give a date when firm numbers will arrive, then deliver early. Potential changes are flagged with a rough number within two days, and no changed work starts without written direction except a real emergency, written up the same day.
WhyOwners rarely remember the problems. They remember who told them the truth early and handled it like an adult.
Many owners here value privacy as much as finish. That is planned like any other scope: confidentiality agreements flowed down to every subcontractor and supplier and explained to the crews, a written photography policy with progress photos taken only by the people named to take them, no personal phone photos of interiors, drones only with written approval, site security suited to the stage of the work, and every question from outside sent to one person.
On an estate the house is often run day to day by an estate manager who will stay long after the builders leave. Commission every system with that person in the room, and hand over a manual worthy of the house: as-built drawings, warranties, operating data, and a finish schedule with paint formulas, stain colors and the makers of every material, so a touch-up in year five matches.
WhyThe estate manager decides who gets the next call. Treat them as the client from the first day.
Every day on a well-run job ends with a short record: the weather, which crews were on site and what they did, deliveries received, inspections passed or failed, visitors, problems and decisions, with dated photographs. It takes ten minutes. Months later it is the answer to every question about when something happened, why a day was lost, what was behind a wall, and whether the work matched the plan. Weekly reports to the owner are built from it.
WhyMemory loses arguments; a dated log with photos settles them. Write it before you leave the site.
The permit comes with an inspection record card that stays on site with the approved plans until the final. Each inspection, from footings and underfloor through framing, rough trades, insulation and drywall to the final, is signed on it in order, and nothing is covered until the inspection for what it hides has been signed. The card and the stamped plans live together in a weatherproof box where the inspector can find them without asking.
WhyInspectors can refuse to inspect without the card and plans on site. Losing the card costs a day; covering work before its signature can cost the wall.
Before the first machine arrives, everyone with a hand in the job sits at one table: owner, architect, builder, and the key trades and consultants. The agenda is practical: site access and parking, working hours, how the neighbors are protected, where materials are staged, who answers which questions, how changes are priced and approved, the inspection sequence, and the decisions the owner owes and by when. The notes go to everyone the same day.
WhyMost of the friction on a job comes from things nobody said out loud at the start. Say them at the precon, and write them down.
The master schedule says when the job finishes; the look-ahead says what happens on Monday. Every week the superintendent updates a three-week view of the work: which trades are coming, what they need ready, which inspections are booked, which deliveries must land and which owner decisions are due. It is posted on site and sent to the trades, so a plumber who is due in two weeks hears now that the framing inspection slipped.
WhyTrades schedule their crews weeks ahead. A look-ahead keeps them coming when they are needed instead of when they are free.
Owners often buy some things themselves: appliances, light fixtures, plumbing trim, hardware, art lighting. That works when the builder knows early. Each item needs its installation instructions and rough-in requirements before the walls close, a delivery date that suits the schedule, someone on site to receive it and check it for damage, and a clear line in the contract for who is responsible if a part is missing or arrives broken.
WhyAn owner-bought range with a different gas or power connection can mean opening a finished wall. Send the spec sheets in design.
On the South Coast nearly all the rain falls between November and April, often in a few big storms. A realistic schedule carries rain days through those months, a number of days the job can lose to weather without moving the finish date, and puts earthwork, foundations and the roof in the dry season where it can. When storms use more than the allowance, the contract says how the time is added.
WhyA schedule with no weather days in winter is not a schedule. Ask how many are carried, and when.
The process page lays out every phase, what you decide in each, and what you hold at the end of it.
The AMN crew trains on the full private set for this trade: a 3D job site you walk station by station, the lesson plan, the field guide, the math and the tools. Sign-in is not needed, but these pages are kept out of search.
The install chapter as a list to walk before you call the work done. Ticks stay in this browser only. Prints on one page.
Construction project management · Job: ________________ · Date: __________ · Checked by: ________________
The same drill our crew uses: give the answer in two sentences before you open each one. If you can only name the thing, read that chapter again.
The cheapest time to stop a project that does not work is before anything is built.
From chapter: A project, in layers
Photos of the open walls are the most useful thing in the binder. They show where every pipe, wire and blocking runs, years later.
From chapter: Your house
A mockup turns "I don't like it" from the end of the job into the beginning, when it costs a panel, not a house.
From chapter: Your house
Plan the crew to the P50, quote the owner the P80, write both down before work starts, and score the job when it ends. The record makes the next estimate honest.
From chapter: Your house
Predictability is the message. Whoever writes the minutes holds the project's memory.
From chapter: Your house
Inspectors can refuse to inspect without the card and plans on site. Losing the card costs a day; covering work before its signature can cost the wall.
From chapter: Your house
19 terms in plain English, with the Spanish our crew uses. All 249 words across the school are on one page.
AMN publishes typical durations including entitlement: renovations about 7 to 21 months end to end, custom residences 17 to 34 months, accessory dwellings 10 to 20 months.
It depends on the parcel: the City of Santa Barbara’s Single Family Design Board or Historic Landmarks Commission, Montecito’s County Board of Architectural Review, Hope Ranch’s Park Homes Association then the County, and the Coastal Commission or local coastal permits in the Coastal Zone.
A written, priced change to the contract, signed before the changed work is done.
AMN builds in three exits: after feasibility, after design development and after entitlement. You keep every report, drawing and permit produced.
A weekly-updated schedule of the next three weeks: which trades come, what they need ready, inspections, deliveries and owner decisions due. It keeps trades arriving when the job is ready for them.
Within 20 days of first furnishing labor or material, to the owner, the general contractor and any construction lender. A late notice protects only the 20 days before it and the work after. This is general information, not legal advice.
A real sample of a finish built on site by the real crew, such as a plaster panel or a stone wall joint. Once approved it is signed and kept, and the finished work is judged against it.
Rules change with each code cycle, and the plans, the inspector, the adopted code and the maker’s instructions overrule any course. Code references are to the 2025 California Building Standards Code (Title 24), in force since 1 January 2026; check the local amendments of the city or county. This page was checked against these on 18 November 2026: