AMN Construction
AMN Construction · The road map

Seven phases. Three exits.

Eighteen months is a long time to wonder. Here is the whole road: every stage, what you receive at each, and three forks where you can leave with everything.

Typical total7–21 months

01020304050607The parcel2 DAYSFeasibility1–4 WEEKSDesign1–4 MONTHSEntitlement6 WK – 9 MOPreconstruction2–4 WEEKSConstruction3–18 MONTHSClosing2-YEAR WARRANTYEXIT ONE · FREEThe written reportThe budgetThe permit pathEXIT TWO · FREEThe full drawing setYours to priceanywhere elseEXIT THREE · FREEIssued permitsIn the property's nameNot oursFIXED PRICE FROM HEREExits — leave with everything produced, at no costThe price becomes binding here
The same seven phases, drawn to time months
03
04
06
Day oneAbout 21 months

On a renovation, the five phases before construction take about 50% of the elapsed time and settle nearly every decision on cost and schedule. The part everyone pictures is the last two blocks on the right.

Drawn for AMN Construction · Tap any stop, or any block on the bar below

Phase 01

The parcel

Two business days

Send whatever exists: an architect's set, a sketch, an address. Matt walks the zoning, constraints and scope himself.

What you receive

  • A written reading of your parcel
  • An order of cost
  • The permit path for your parcel
  • The review bodies your address answers to, named

Phase 02

Feasibility

One to four weeks

Utility capacity, access, soils where they matter, and a preliminary budget built from line items, not an average per square foot.

What you receive

  • A line-item preliminary budget
  • Site constraints and utility findings
  • A preliminary schedule with agency dates

Exit one

A written budget and a feasibility reading. If the numbers don't work, it ends here.

You leave with

  • The written feasibility report
  • The line-item preliminary budget
  • Site and utility findings
  • The permit path — yours to take elsewhere

Phase 03

Design development

Four weeks to four months

Drawings carried to a standard that can be priced and permitted, reviewed for constructability throughout, not after.

What you receive

  • A permit-ready set
  • Structural and Title 24 coordination
  • A budget revised against real drawings
  • A written constructability review

Exit two

The drawings you paid for are yours, to price with another builder if you wish.

You leave with

  • The full permit-ready set
  • Structural and Title 24 coordination
  • The revised budget
  • No penalty and no clawback

Phase 04

Entitlement

Six weeks to nine months

We submit, answer plan check and hold the agency relationship. Coastal, architectural review and variance triggers were identified in Phase 01.

What you receive

  • A submitted and tracked application
  • Plan check corrections answered in writing
  • Issued permits

Exit three

Approved permits attach to the property, not to us.

You leave with

  • Issued permits in the property's name
  • All plan-check correspondence
  • Permits that stay with the property
  • No construction commitment

Phase 05

Preconstruction

Two to four weeks

Trades bid the permitted set; allowances become selections. We open walls on purpose here, so what is behind them is priced, not discovered.

What you receive

  • A fixed contract sum: the number is set here
  • A confirmed schedule
  • An allowance schedule with dated decision deadlines

Phase 06

Construction

Three to eighteen months

Matt is on site. A written Friday account with photographs, a live schedule, and any cost movement in writing before the work occurs.

What you receive

  • A written update every Friday
  • Variations priced in writing, in advance
  • A single point of accountability

Phase 07

Closing and warranty

Ongoing

Final inspection, a punch walk you lead, and the full documentation package. The person who will live there writes the better list.

What you receive

  • A punch list closed to your satisfaction
  • Warranties, manuals, and as-builts
  • Two years of workmanship coverage
  • A twelve-month return visit, called for or not

On a calendar

Start this month. Finish when?

The seven phases on real months, rainy season marked. Choose the project, the month we first talk, and how smoothly review goes.

The building year

Twelve months on the South Coast, and what each one asks of a project.

Rain decides when earth can move, wind decides what a house must be made of, and the coast has its own calendar besides. Choose a month.

4.44.43.21.01.43.1JANFEBMARAPRMAYJUNJULAUGSEPOCTNOVDECSEP0.05 in

This month

September

0.05 inaverage rain78° / 60°average high and low

Still dry, and still warm. The months left before the rain are the ones to use for anything that must be closed in.

  • Rainy season for gradingCounty grading code: November 1 to April 15
  • Sundowner winds, most frequentSpring, typically beginning near sunset
  • May gray and June gloomMarine layer mornings
  • Gray whales, then blue whalesGray December to May; blue late May to September
  • Monarchs at EllwoodOctober to February
  • Seal pups at CarpinteriaRookery beach closed December 1 to May 31
  • Plovers nestingMarch 15 to September 15
Average rain and temperature by month, Santa Barbara
MonthRainHigh / low
January4.43 in67° / 46°
February4.41 in67° / 47°
March3.20 in68° / 49°
April1.01 in71° / 51°
May0.41 in72° / 54°
June0.14 in73° / 57°
July0.01 in76° / 60°
August0.01 in78° / 60°
September0.05 in78° / 60°
October0.84 in76° / 56°
November1.40 in71° / 50°
December3.07 in66° / 46°

Rain and temperature: NOAA 1991–2020 normals, Santa Barbara. Seasons: County of Santa Barbara grading code; UCSB; NOAA Channel Islands; City of Goleta; City of Carpinteria; UCSB Coal Oil Point Reserve.

Evidence

Every claim above has a document behind it.

A process page is easy to write and hard to prove. So we publish the specimens: an allowance schedule, a Friday update, the change-order clause in our standard wording, and when the price stops moving.

See the documents

Inquiries

Send us the address. We'll tell you the truth about it.

Email it to purchasing@amnbuild.com. A written assessment, free, in two business days. Yours to keep, whether or not we build together.

  1. Same dayMatt confirms he has it, and flags anything obvious that is missing.
  2. Within two business daysA written reading of your parcel: jurisdiction, review bodies, constraints, an order of cost and the permit path.
  3. Then nothing, unless you askNo follow-up sequence, no call from anyone else. The assessment is yours to keep, and to take anywhere.
Email Matt